PSPCL leaves farmer waiting over two months despite week-long assurance


Raghbir Singh Brar

Faridkot

raghbirsinghbrar@gmail.com

If you believe that the functioning of government offices in Punjab has changed under the Bhagwant Mann-led AAP government, my recent experience proves otherwise. This is a first-hand account of how files actually move—or fail to move—in public offices, beginning with the Punjab State Power Corporation Limited (PSPCL) Sub-Division (Sub-Urban) in Kotkapura.

When my existing borewell in Khasra No. 378 failed, I was forced to dig a new borewell just a few metres away within the same land parcel as an emergency measure to save my standing crop.

On September 9, 2026, I submitted a complete application file along with all required documents at the office of the Sub-Divisional Officer (SDO), Sub-Urban, Kotkapura. Along with requesting the shifting of my tubewell connection, I also opted for the Voluntary Disclosure Scheme (VDS) and deposited the requisite fee to increase my sanctioned load from 5 BHP.

However, more than two months later, neither has a new transformer been provided nor has my file for shifting the motor connection moved an inch.

When I submitted the documents, the consumer clerk assured me: “I have received your file, and its entry number is 179. We will trace your old file and contact you within a week.”

After waiting for weeks with no response, I called the clerk myself. He informed me that my old file had been traced and claimed the matter was “under process.” Since then, there has been complete silence.

Under PSPCL rules, once an application is submitted to shift a tubewell connection within the same Khasra number, the file is supposed to be forwarded to the concerned Junior Engineer (JE) to estimate the cost of lengthening or shortening the power line. Furthermore, if the consumer agrees to bear the cost of uprooting and reinstalling the line, PSPCL does not recover those charges, levying only a nominal processing fee.

Despite fulfilling every requirement, my file remains stalled—perhaps because I neither personally approached senior officials nor brought in political recommendations.

What is the Voluntary Disclosure Scheme (VDS)?

Explaining the provision, senior Faridkot-based advocate Ashu Mittal said, “Voluntary disclosure applies when a consumer had not previously declared an upgrade. For instance, if a farmer had a sanctioned load of 5 BHP and, due to an emergency, installed a new borewell and increased the load to 10 BHP, that additional consumption would technically be unauthorised. By opting for VDS and paying the prescribed fee, the consumer officially declares the enhanced load, thereby regularising the connection as per government guidelines.”